cost breakdown in table
This commit is contained in:
		
							
								
								
									
										
											BIN
										
									
								
								last_mile_distribution_box.png
									
									
									
									
									
										Normal file
									
								
							
							
						
						
									
										
											BIN
										
									
								
								last_mile_distribution_box.png
									
									
									
									
									
										Normal file
									
								
							
										
											Binary file not shown.
										
									
								
							| 
		 After Width: | Height: | Size: 1.9 KiB  | 
							
								
								
									
										
											BIN
										
									
								
								main_distribution_box.png
									
									
									
									
									
										Normal file
									
								
							
							
						
						
									
										
											BIN
										
									
								
								main_distribution_box.png
									
									
									
									
									
										Normal file
									
								
							
										
											Binary file not shown.
										
									
								
							| 
		 After Width: | Height: | Size: 1.7 KiB  | 
							
								
								
									
										
											BIN
										
									
								
								network_operations_center.png
									
									
									
									
									
										Normal file
									
								
							
							
						
						
									
										
											BIN
										
									
								
								network_operations_center.png
									
									
									
									
									
										Normal file
									
								
							
										
											Binary file not shown.
										
									
								
							| 
		 After Width: | Height: | Size: 2.1 KiB  | 
							
								
								
									
										11
									
								
								proposal.md
									
									
									
									
									
								
							
							
						
						
									
										11
									
								
								proposal.md
									
									
									
									
									
								
							@@ -36,9 +36,14 @@ The project cost breakdown includes the necessary equipment and components for t
 | 
			
		||||
 | 
			
		||||
The cost breakdown for the cable installation project is as follows:
 | 
			
		||||
 | 
			
		||||
- MVR 265,000 for cables, distribution box, splitters, patch cords, and ODF.
 | 
			
		||||
- MVR 60,000 for splicing works (with potential for cost reduction through optimization).
 | 
			
		||||
- MVR 20,000 for the OLT (control device).
 | 
			
		||||
 | 
			
		||||
| Cost Component          | Amount (MVR) |
 | 
			
		||||
|------------------------|--------------|
 | 
			
		||||
| Cables and Equipment   | 265,000      |
 | 
			
		||||
| Splicing Works         | 60,000       |
 | 
			
		||||
| OLT (Control Device)   | 20,000       |
 | 
			
		||||
| Digging Labor (Estimate)| To be arranged by council |
 | 
			
		||||
| Total Project Cost     | 345,000      |
 | 
			
		||||
 | 
			
		||||
The total project cost amounts to MVR 345,000, which can be paid within a span of 1 year through monthly installments of MVR 28,750. Additionally, there is a one-time payment of MVR 1000 for the OLT (client router).
 | 
			
		||||
 | 
			
		||||
 
 | 
			
		||||